The City routinely evaluates road condition and maintains a priority based resurfacing program based on a Pavement Condition Index (PCI) score. The City employs an independent third party to survey and rate all City-owned roads using the ASTM 6433 Standard Practice for roads and Parking Lots Pavement Condition Index Surveys. The latest PCI report is available at this link

Streets remain open during resurfacing work; however, please makes sure vehicles are not parked in the roadway. If you have a sprinkler system, please ensure that the system is not spraying water into the road. Expect minor delays accessing your street while crews are working.

The work is done in phases:

  • Phase 1: Notice - Our goal is to provide at least one week's notice. The schedule takes into account weather and time to complete the roads in progress.
  • Phase 2: Milling - Crews mill (grind up) the old asphalt. Following the mill process, it can take up to 7 days before paving takes place.
  • Phase 3: Paving
  • Phase 4: Clean Up - Public Works crews inspect the quality of the paving work and the clean up the area as needed. If additional work is required, it is scheduled and typically completed within three business days.

Paving Schedule

Paving Schedule: June 24, 2024

Street Name From Street To Street Work Beginning   
ROYERVISTA DR EOP ROYER PL Ongoing  
ROYERVISTA DR ROYER PL ROYER CT Ongoing  
BRANSFORD RD HIGH POINT RD SHIVER SMT Ongoing  
TAMARISK DR HIGH POINT RD CUL-DE-SAC Ongoing  
ELDEN DR GREEN HILL PL GREEN HILL PL Ongoing  
TIMBER TRL S CUL-DE-SAC TIMBERLAND DR June 21, 2024  
TIMBER TRL S TIMBERLAND DR TIMBER VALLEY RD June 21, 2024  
HIGH BROOK DR CUL-DE-SAC HIGH POINT RD June 24, 2024  
WINDSOR PKWY HEDDEN ST BRINKLEY LN June 26, 2024  
WINDSOR PKWY NORTHLAND DR WINDSOR GATE CT June 26, 2024  
WINDSOR PKWY WINDSOR PKWY WINDSOR PKWY June 26, 2024  
WINDSOR PKWY WINDSOR PKWY WINDSOR CT June 26, 2024  
HIGHGROVE POINTE WINDSOR PKWY CUL-DE-SAC June 28, 2024  
VALLEYFIELD DR DUNCOURTNEY DR CUL-DE-SAC June 25, 2024  
FIRE STATION  SPAULDING DR  MT VERNON RD  June 25, 2024  
CURRY DR WOODCHASE CT PEACHTREE DUNWOODY RD July 1, 2024  
CURRY DR WOODCHASE CT CUL-DE-SAC July 1, 2024  
WOODMOORE CT S TRIMBLE RD CUL-DE-SAC July 3, 2024  
RIVEREDGE PKWY RIVEREDGE PKWY EOP July 8, 2024  
PERIMETER CTR W MARTRA TRAFFIC SIGNAL TRAFFIC SIGNAL AT 1165
PERIMETER CTR W
July 11, 2024  
         
Long Title
Roadway Maintenance and Paving
Tags
Date
-
Page Layout